EQS-Adhoc: NEXTDC Limited: M3 Melbourne Power Delay and Revised FY27 Guidance

EQS-Ad-hoc: NEXTDC Limited / Key word(s): Statement/Statement
 NEXTDC Limited: M3 Melbourne Power Delay and Revised FY27 Guidance

 20-Oct-2026 / 23:39 CET/CEST
 Disclosure of an inside information acc. to Article 17 MAR of the Regulation
 (EU) No 596/2014, transmitted by [1]EQS News - a service of [2]EQS Group.
 The issuer is solely responsible for the content of this announcement.

 ═══════════════════════════════════════════════════════════════════════════════

 NEXTDC Limited (ASX:NXT) ('NEXTDC' or the 'Company'). The ASX Market
 Announcement of the below release can also be viewed at
 [3]www.nextdc.com/investor-centre. The information is being provided for the
 holders of NEXTDC's A$1,100,000,000 1.75 per cent. Subordinated Convertible
 Notes due 2031 (ISIN XS3485473303) admitted to trading on the Vienna MTF of the
 Vienna Stock Exchange.

 ASX Release
 21 October 2026
   M3 Melbourne Power Delay and Revised FY27 Guidance NEXTDC Limited (ASX: NXT)
 (“NEXTDC” or the “Company”) revises its net revenue, earnings and capital
 expenditure guidance for the financial year ending 30 June 2027 (“FY27”),
 together with an update on its liquidity position at 30 September 2026.
 The revision primarily reflects delays to electricity network works by Jemena
 Electricity Networks (Vic) Ltd (“Jemena”), which defer the next increase in
 grid supply to NEXTDC’s M3 Melbourne data centre (“M3”) and, with it, the
 delivery and billing of contracted capacity. Jemena has advised NEXTDC that it
 has suspended parts of those works because of community and stakeholder
 opposition. Summary[4][1]

   • M3 Melbourne power: delays to Jemena’s electricity network works mean the
     next increase in grid supply to M3 is now expected in FY28, deferring the
     delivery and billing of contracted capacity. The Victorian Government’s
     planning decision on M3 Stages 6 and 7 is now expected only after the
     Victorian State election on 28 November 2026
   • FY27 net revenue[5][2] guidance revised, excluding the affected M3
     contracts: A$475 million to A$500 million, down from A$615 million to A$640
     million[6][3]
   • FY27 Underlying EBITDA[7][4] guidance revised, excluding the affected M3
     contracts: A$245 million to A$265 million, down from A$385 million to A$410
     million3
   • FY27 capital expenditure guidance revised: A$4,500 million to A$5,000
     million, down from A$5,250 million to A$5,750 million[8][5]
   • Liquidity: A$8,675 million of liquidity at 30 September 2026[9][6]
   • Covenants and maturities: in compliance with financial covenants; earliest
     scheduled debt maturity is December 2029, with a potential Convertible
     Notes holder put option on 17 September 2029[10][7]

 The Company’s revised FY27 net revenue and Underlying EBITDA guidance excludes
 the revenue and attributable EBITDA of the affected customer contracts at M3
 Melbourne, including capacity already billing and any potential service level
 credits.
 NEXTDC remains in compliance with its financial covenants and will refocus its
 capital expenditure on near term contracted customer capacity, eliminating all
 material discretionary capital expenditure. It has begun a detailed review of
 its capital expenditure program and will announce the outcome by its Annual
 General Meeting on 20 November 2026. The Board will also evaluate capital
 recycling opportunities, including the potential sale of selected development
 sites that are not required in the near term.
 NEXTDC Chief Executive Officer and Managing Director, Craig Scroggie, said:
 “Jemena has suspended parts of the network works required for the next increase
 in grid supply to M3 Melbourne. Jemena has attributed the suspension to
 community and stakeholder opposition to the works and to the absence of local
 council consent pending further consultation. On Jemena’s current indicative
 estimate, we expect that increase during FY28.
 “We have taken the affected M3 contracts out of FY27 guidance until we can
 reliably estimate their contribution. The August guidance included
 approximately A$140 million of each of net revenue and Underlying EBITDA from
 those contracts. The timing and scale of their contribution remain uncertain.
 “The capacity remains under contract, subject to the customer’s rights, and
 construction of the data halls is continuing. We are working with our customer
 on a revised power ramp and with Jemena to bring power forward.
 “With M3 revenue deferred, we have paused projects not backed by customer
 contracts and put that capital behind the capacity our customers have already
 contracted. We have approximately A$8.7 billion of liquidity at 30 September
 2026 and we are in compliance with our covenants.” M3 Melbourne power delay and
 Stages 6 and 7 development approval NEXTDC’s M3 Melbourne data centre is
 affected by delays to third-party electricity network works, in particular to
 the 66kV line augmentation works of Jemena, the electricity distributor that
 supplies power to M3. Jemena suspended parts of those works in September 2026
 and has since formally notified NEXTDC that it does not expect to recommence
 them before February 2027. Jemena has attributed the suspension to safety
 concerns and lack of access to work sites arising from community and
 stakeholder opposition to the works and to the local council, as the relevant
 road authority, not giving its consent while further community consultation
 takes place. Jemena is consulting the community and other stakeholders and
 seeking the approvals required to recommence the works safely. NEXTDC supports
 that consultation. Whilst NEXTDC already engages with the community around M3,
 including through dedicated community engagement staff and newsletters on works
 and activities at the site, it intends to continue and build on that through a
 community engagement plan for the construction and operation of M3, overseen by
 the Board.
 Grid supply at M3 is expected to increase in stages. The first increase depends
 on Jemena’s works. Based on Jemena’s current indicative estimate, NEXTDC
 expects that increase during FY28, with delivery and billing of the contracted
 capacity that depends on it to follow shortly thereafter.
 Later increases in grid supply at M3 depend on upstream transmission projects
 to install new transformers at the Brooklyn Terminal Station. NEXTDC now
 expects the first of these projects to be completed later than previously
 expected. The Brooklyn Terminal Station upstream projects do not separately
 affect the revised FY27 net revenue and Underlying EBITDA guidance, but they
 affect the timing of capacity expected to convert to billing after FY28.
 Construction of the M3 data halls is continuing within the existing buildings.
 However, the Victorian Government’s planning decision on a planning permit for
 M3 Stages 6 and 7 (application PA2604231) is taking longer than NEXTDC
 expected. The application was lodged in February 2026 under the Victorian
 Government’s Development Facilitation Program, which is available to eligible
 data centre projects, and is for the planned expansion of NEXTDC’s approved and
 partly operational M3 campus. The Victorian Government is due to become subject
 to caretaker conventions from 3 November 2026 pending the State election on 28
 November 2026, and NEXTDC does not now expect that decision until 2027.
 Assuming the permit is granted, the later decision, together with the later
 grid supply, delays delivery of the final stages of capacity at M3.
 NEXTDC has a good relationship with the affected customer and will continue to
 engage constructively with it. NEXTDC intends to work closely with the customer
 and with Jemena to bring forward the delivery of power to M3 and to minimise
 the impact of the delays. NEXTDC is also assessing the potential implications
 of the delays under the affected customer contracts. Those contracts provide
 for service level credits where capacity is delivered late or is not fully
 powered and, in some circumstances, give the customer rights to terminate. As
 part of that assessment, NEXTDC is considering whether relief is available to
 it under the force majeure and other relevant provisions of those contracts.
 The capacity deferred by the delays to Jemena’s works remains under contract,
 subject to the customer’s rights.
 NEXTDC will provide further updates, including at its Annual General Meeting on
 20 November 2026. Trading update FY27 net revenue and Underlying EBITDA

 NEXTDC now expects FY27:

   • Net revenue of A$475 million to A$500 million, down from its previous
     guidance of A$615 million to A$640 million.
   • Underlying EBITDA of A$245 million to A$265 million, down from its previous
     guidance of A$385 million to A$410 million.

 The revised net revenue and Underlying EBITDA guidance excludes the revenue and
 attributable EBITDA of the affected customer contracts at M3 Melbourne,
 including capacity already billing and any potential service level credits.
 Capacity already billing is excluded because, while parts of Jemena’s works are
 suspended, existing grid supply at M3 cannot be relied on to support the full
 contracted power ramp in data halls already delivered. NEXTDC is working with
 the affected customer on a revised power ramp. The guidance of 27 August 2026
 included approximately A$140 million of each of net revenue and Underlying
 EBITDA from those contracts, and their exclusion is the main reason for the
 reductions in net revenue and Underlying EBITDA guidance. In all other
 respects, the revised net revenue and Underlying EBITDA guidance is given on
 the same basis as the guidance of 27 August 2026: on a constant currency basis,
 with Underlying EBITDA excluding the items described in footnote 4. NEXTDC’s
 actual FY27 results will include the contribution of the affected customer
 contracts. Service level credits payable on those contracts could reduce
 Underlying EBITDA below the revised guidance.
 NEXTDC cannot yet reliably estimate the FY27 contribution of the affected
 customer contracts at M3 Melbourne, which depends on its discussions with the
 affected customer, the customer’s assessment of its rights and obligations
 under those contracts, whether relief is available to NEXTDC under their force
 majeure and other relevant provisions and the accounting for any service level
 credits. NEXTDC will update the market when it can reliably estimate that
 contribution. Changes in the expected timing and cost of completing M3
 Melbourne are also likely to affect the fair value of NEXTDC’s investment
 properties. NEXTDC has not yet quantified that effect and will reflect it in
 its results for the half year ending 31 December 2026. The revised FY27
 guidance is given before any fair value movement on investment property. FY27
 capital expenditure

 NEXTDC now expects FY27:

   • Capital expenditure of A$4,500 million to A$5,000 million, a reduction of
     A$750 million, or 13% to 14%, from its previous guidance of A$5,250 million
     to A$5,750 million[11][8].

 NEXTDC has begun a detailed review of its capital expenditure program. The
 Board has committed to announcing the outcome of that review by NEXTDC’s Annual
 General Meeting on 20 November 2026. NEXTDC’s revised FY27 capital expenditure
 guidance of A$4,500 million to A$5,000 million reflects a focus solely on
 delivering new contracted customer capacity expected to be delivered in the
 next 12 to 18 months or development works largely advanced to near completion.
 The revised capital expenditure guidance includes approximately A$500 million
 of reimbursable customer fitout and approximately A$230 million of capitalised
 interest. The previous guidance did not include capitalised interest. Before
 capitalised interest, the revised guidance is approximately A$4,270 million to
 A$4,770 million, a like for like reduction of approximately A$980 million, or
 17% to 19%, from the previous guidance. The reduction primarily reflects the
 deferral of spend on uncontracted data centre expansion projects and on
 corporate technology and other projects.
 To prioritise near term contracted customer capacity, NEXTDC has put all new
 development projects and land acquisitions on hold for the foreseeable future.
 The Board will also evaluate capital recycling opportunities, including the
 potential sale of selected development sites that are not required in the near
 term. Liquidity and covenants At 30 September 2026, NEXTDC had liquidity of
 A$8,675 million, comprising A$1,275 million of cash and A$7,400 million of
 undrawn senior debt facilities and Hybrid Securities.
 NEXTDC remains in compliance with its financial covenants as at 30 June 2026,
 the most recent half-yearly test date, and expects to comply with them at the
 next test date of 31 December 2026.
 NEXTDC’s maintenance financial covenants, being a gearing ratio of not more
 than 60% and an interest cover ratio of at least 1.5 times[12][9], are given
 under the Common Terms Deed Poll (“CTDP”), which applies only to its senior
 debt facilities. The interest cover covenant allows NEXTDC to include the
 annualised EBITDA of new customer contracts expected to start billing within 24
 months of each calculation date.
 NEXTDC’s ability to draw all of its A$6,700 million undrawn senior debt
 facilities while continuing to comply with those covenants will depend on the
 timing of drawdowns and on the expected billing profiles of its new customer
 contracts at that time. If there was a material change to expected customer
 billing profiles, NEXTDC’s ability to draw down senior debt may be adversely
 affected. Delays to grid supply at M3 Melbourne could be such a change.
 The Subordinated Notes, Hybrid Securities and the A$1,100 million of 1.75%
 Subordinated Convertible Notes due 2031 (“Convertible Notes”) issued on 17
 September 2026 sit outside those covenants and carry no maintenance financial
 covenants[13][10]. The Subordinated Notes and Hybrid Securities include an
 incurrence gearing ratio of not more than 85%.
 NEXTDC will continue to assess the effect of the delays to grid supply at M3
 Melbourne on its debt facilities, including on its ability to draw down senior
 debt while continuing to comply with its financial covenants. Investor briefing
 NEXTDC will host an investor briefing on this release at 9:30am (AEDT) on
 Wednesday 21 October 2026. The briefing will be webcast at
 [14]https://edge.media-server.com/mmc/p/pvmmxoga Forward-looking statements
 This release contains forward-looking statements, including the revised FY27
 guidance and the expected timing of grid supply, capacity delivery and billing
 at M3. They are based on management’s current expectations and assumptions, are
 not guarantees of future performance and are subject to known and unknown risks
 and uncertainties, many of which are beyond NEXTDC’s control, that could cause
 actual results to differ materially. There can be no assurance that actual
 outcomes will not differ materially from these statements. There are usually
 differences between forecasts and actual results because events and
 circumstances frequently do not occur as forecast, and these differences may be
 material.
 Investors should not place undue reliance on forward-looking statements,
 especially in view of current economic conditions, supply chain issues and
 other uncertainty and disruption. None of NEXTDC, any member of the NEXTDC
 group or their respective officers, employees, agents or any other person gives
 any warranty, representation or assurance that any event expressed or implied
 in any forward-looking statement will occur.
 NEXTDC does not undertake to update forward-looking statements to reflect any
 change in its circumstances, financial condition or affairs or in the events or
 conditions on which such statements are based, except as required by law or the
 ASX Listing Rules.
 Authorised for release by the Board of NEXTDC Limited.
 ENDS
 For more information:

 Investor enquiries                                                      Media
 enquiries
 Simon Guzowski                                                      Ben Wilson
 T: +61 2 8072 4943                                                    Senior
 Managing Director, Teneo
 E: [15][email protected]                                M: +61 407
 966 083
                                                                                
 E: [16][email protected]

 NEXTDC Investor Centre: [17]www.nextdc.com/investor-centre
 About NEXTDC
 NEXTDC is an ASX 100-listed technology company and Asia’s most innovative Data
 Centre-as-a-Service provider. We are building the infrastructure platform for
 the digital economy, delivering the critical power, security and connectivity
 for global cloud computing providers, enterprise, and Government.

 NEXTDC is recognised globally for the design, construction, and operation of
 Australia’s only network of Uptime Institute certified Tier IV facilities and
 is one of the first data centre operators in the Southern Hemisphere to achieve
 Tier IV Gold certification for Operational Sustainability. NEXTDC has a strong
 focus on sustainability and operational excellence through renewable energy
 sources and delivering world-class operational efficiency. NEXTDC’s corporate
 operations have been certified carbon neutral under the Australian Government’s
 Climate Active Carbon Neutral Standard.

 Our Cloud Centre partner ecosystem is Australia’s most dynamic digital
 marketplace, comprising carriers, cloud providers and IT service providers,
 enabling local and international customers to source and connect with cloud
 platforms, service providers and vendors to build complex hybrid cloud networks
 and scale their critical IT infrastructure services.

 NEXTDC is powering the intelligence economy.
 To learn more, visit [18]www.nextdc.com
  

 ═══════════════════════════════════════════════════════════════════════════════

 [19][1]   Refer to further detail below under “Trading update”
 [20][2]   Comprises total revenue less direct costs
 [21][3]   The revised net revenue and Underlying EBITDA guidance excludes the
 revenue and attributable EBITDA of the affected customer contracts at M3
 Melbourne, including capacity already billing and any potential service level
 credits. The guidance of 27 August 2026 included those contracts. Service level
 credits payable on those contracts could reduce Underlying EBITDA below the
 revised guidance
 [22][4]   FY27 Underlying EBITDA excludes non-recurring items, costs of
 assessing acquisition opportunities, the Growth Incentive Plan announced on 24
 February 2025 and costs of international markets other than Malaysia, which is
 no longer an early-stage market following the commissioning of KL1 Kuala Lumpur
 in May 2026. FY27 guidance is also given before any fair value movement on
 investment property
 [23][5]   FY27 guidance was provided on 27 August 2026 on a constant currency
 basis and did not include capitalised interest in capital expenditure guidance.
 The revised capital expenditure guidance includes approximately A$230 million
 of capitalised interest
 [24][6]   Liquidity comprises cash of A$1,275 million, undrawn senior debt
 facilities of A$6,700 million and the A$700 million Hybrid Securities B Delayed
 Draw Series, which is committed, subject to customary conditions, and may be
 drawn until 15 April 2027, each at 30 September 2026. Liquidity is non-IFRS
 financial information and has not been subject to audit or review
 [25][7]   Being the A$1,500 million Facility A revolving loan facility, which
 matures on 3 December 2029. Holders of the Convertible Notes may require NEXTDC
 to redeem them on 17 September 2029 at their principal amount plus accrued
 interest
 [26][8]   See footnote 5 above
 [27][9]   Both covenants are set by the CTDP dated 3 November 2024, as amended.
 The gearing ratio is net senior debt divided by total assets at book value,
 attributable to the Australian group. Net senior debt is total debt less total
 cash, where total debt excludes subordinated debt such as the Subordinated
 Notes, Hybrid Securities and Convertible Notes. The interest cover ratio is
 EBITDA, as defined in the CTDP, for the 12 months to each calculation date,
 divided by net interest expense. Net interest expense is interest expense,
 including capitalised interest and recurring commitment and line fees, less
 interest received, and excludes interest on that subordinated debt whose terms
 allow its interest to be deferred or capitalised, or not to be paid in cash
 during an event of default in respect of senior debt
 [28][10]  The Subordinated Notes and Hybrid Securities are subject to an
 incurrence covenant under which debt or hybrid issuances, material asset
 disposals and equity distributions may be made only if the Adjusted Gearing
 Ratio, inclusive of all debt of NEXTDC and its subsidiaries (including the
 Hybrid Securities) and adjusted for the relevant transaction, does not exceed
 85%

  

 End of Inside Information

 ═══════════════════════════════════════════════════════════════════════════════

 20-Oct-2026 CET/CEST News transmitted by [29]EQS Group

 View original content: [30]EQS News

 ═══════════════════════════════════════════════════════════════════════════════

   Language:    English
   Company:     NEXTDC Limited
                20 Wharf Street
                4000 Brisbane City
                Australia
   ISIN:        AU000000NXT8
   Listed:      Vienna Stock Exchange (Vienna MTF)
   LEI Code:    529900RTERU3X7G3D672
   EQS News ID: 2419144


    
   End of Announcement EQS News Service


   2419144  20-Oct-2026 CET/CEST

   https://nwr.eqs-cockpit.com/fncls2.ssx?application_id=2419144&application_name=news&site_id=apa_ots_austria~~~18b544d0-9c71-4160-bd95-cc8b9aff9fbf

References

   Visible links
   1. https://nwr.eqs-cockpit.com/fncls2.ssx?fn=redirect&url=2be925ac0334ae7b4f51fbaee4a6daf0&application_id=2419144&site_id=apa_ots_austria~~~18b544d0-9c71-4160-bd95-cc8b9aff9fbf&application_name=news
   2. https://nwr.eqs-cockpit.com/fncls2.ssx?fn=redirect&url=f5d50dc7e8798b6eb177f7955e598e60&application_id=2419144&site_id=apa_ots_austria~~~18b544d0-9c71-4160-bd95-cc8b9aff9fbf&application_name=news
   3. https://nwr.eqs-cockpit.com/fncls2.ssx?fn=redirect&url=877ac4d8ce49296440212f88ec34811e&application_id=2419144&site_id=apa_ots_austria~~~18b544d0-9c71-4160-bd95-cc8b9aff9fbf&application_name=news
   4. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn1
   5. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn2
   6. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn3
   7. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn4
   8. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn5
   9. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn6
  10. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn7
  11. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn8
  12. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn9
  13. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftn10
  14. https://nwr.eqs-cockpit.com/fncls2.ssx?fn=redirect&url=b73ab3f296668f1af75db59fe66f0625&application_id=2419144&site_id=apa_ots_austria~~~18b544d0-9c71-4160-bd95-cc8b9aff9fbf&application_name=news
  15. mailto:[email protected]
  16. mailto:[email protected]
  17. https://nwr.eqs-cockpit.com/fncls2.ssx?fn=redirect&url=877ac4d8ce49296440212f88ec34811e&application_id=2419144&site_id=apa_ots_austria~~~18b544d0-9c71-4160-bd95-cc8b9aff9fbf&application_name=news
  18. https://nwr.eqs-cockpit.com/fncls2.ssx?fn=redirect&url=992fab530c462d097368bba02de54766&application_id=2419144&site_id=apa_ots_austria~~~18b544d0-9c71-4160-bd95-cc8b9aff9fbf&application_name=news
  19. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref1
  20. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref2
  21. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref3
  22. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref4
  23. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref5
  24. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref6
  25. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref7
  26. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref8
  27. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref9
  28. file:///appl/crsred1/tmp/HTML-FormatExternal-q61yuR.html#_ftnref10
  29. https://nwr.eqs-cockpit.com/fncls2.ssx?fn=redirect&url=f5d50dc7e8798b6eb177f7955e598e60&application_id=2419144&site_id=apa_ots_austria~~~18b544d0-9c71-4160-bd95-cc8b9aff9fbf&application_name=news
  30. https://nwr.eqs-cockpit.com/fncls2.ssx?fn=redirect&url=84fafece332ab290c5b44c9d42422b7a&application_id=2419144&site_id=apa_ots_austria~~~18b544d0-9c71-4160-bd95-cc8b9aff9fbf&application_name=news

OTS-ORIGINALTEXT PRESSEAUSSENDUNG UNTER AUSSCHLIESSLICHER INHALTLICHER VERANTWORTUNG DES AUSSENDERS - WWW.OTS.AT |

Bei Facebook teilen.
Bei X teilen.
Bei LinkedIn teilen.
Bei Xing teilen.
Bei Bluesky teilen

Stichworte

Channel